Updates from the Village Administrator, Chris Edds.

September 23rd, 2019 – October 15th, 2019

  1. Zoning.
  2. Permits.
  3. Create ad for Part-Time position.
  4. 3 hr meeting with Mr. McDaniel from the EPA in regards to 230 W Center St.
  5. Detailed letter Drafted and sent to Mr. McDaniel in regards to hydrant flushing.
  6. Contact AOP for quote to inspect filter media at WTP as well as provide a quote to clean clear well and reaction basin’s.
  7. Water shut offs.
  8. Building permits issued.
  9. Attach all residences’ on the Hemple Rd project area to new water main.
  10. Read meters.
  11. Try to locate water service to 12520 Hemple Rd. I contacted MR Tim Ballard from Ohio Rural Water to help locate said service. After approx. 3 hrs, we thought we had the service located. The following day, we rented a mini excavator and dug 10 ft past the markings that were thought to be the water line. With the water line being plastic with no tracer wire, it was near impossible to find. Between the engineer and I we were able to resolve the issue and now the resident is tied into the new water main.
  12. 4” Transite water main has now been abandoned on Hemple Rd.
  13. Prep to flush hydrants. Crews ran into several issues, but they were soon corrected.
  14. Pass out Boil advisories to affected residents in the Hemple Rd Phase 3 project area and several on Dean Dr. This was due to the tie into the 10” water main from Dean Dr. to the 12” water main on Hemple Rd. This was strictly precautionary and was lifted the following day after our lab stated that the water was free from bacteria.
  15. Flushed Hydrants on the distribution system. This was a 2 day event and was completed on Thursday, October 11th.
  16. Check progress of Hemple Rd.
  17. Pick up Dump Truck from Longs Truck and Trailer after repairs have been made.
  18. Check lift station pump @ Elm St. Found that Pump will have to be repaired/ replaced due to bad winding.
  19. Sort through Resumes that have been submitted for open Part-Time position.
  20. Prep for council.
  21. Daily lab duties for WTP and WWTP.
  22. Complete OPWC in-kind sheets for Hemple Rd Phase 3.

September 9th, 2019 - October 15th, 2019

August 12th, 2019 - September 9th, 2019

July 8th, 2019 - August 12th, 2019

June 10th, 2019 - July 8th, 2019

May 28th, 2019 - June 10th, 2019

May 13th 2019 - May 27th 2019

April 22nd, 2019 - May13th, 2019

April 8th, 2019 - April 22nd, 2019

March 26th, 2019 - April 8th, 2019

March 11th, 2019 - March 25th, 2019

February 25th, 2019 - March 11th, 2019

February 11th, 2019 - February 25th, 2019

January 28th, 2019 - February 11th, 2019

January 14 th, 2019 - January 28th, 2019

December 10th, 2018 - January 14th, 2019

November 26th, 2018 - December 10th, 2018

November 13th, 2018 - November 26th, 2018

October 22nd, 2018 - November 13th, 2018

October 8th, 2018 - October 22nd, 2018

September 24th, 2018 - October 8th, 2018

September 10th, 2018 - September 24th, 2018

August 14th, 2018 - September 10th, 2018

July 10th, 2018 - August 13th, 2018

June 11th, 2018, - July 9th, 2018

May 29th, 2018 - June 10th, 2018

May 14th, 2018 - May 29th, 2018

April 23rd, 2018 - May 14th, 2018

April 8th, 2018 - April 22nd, 2018

March 26th, 2018 - April 9th, 2018

March 12th, 2018 - March 26th, 2018