Updates from the Village Administrator, Chris Edds.

February 24th, 2020 – March 9th, 2020

  1. Zoning.
  2. Permits.
  3. Daily checks at WWTP and WTP.
  4. Prep for council.
  5. Backwash WTP.
  6. Prep to remove trees in easement on Dean Dr.
  7. Receive parts for dump truck to replace failing air tanks. Replaced air tanks and leak checked. No leaks were found and dump truck was placed back in service.
  8. Waste sludge.
  9. Pull samples for sludge to be hauled.
  10. Contact Dwayne Miller with Miller Land Application to see when we can haul sludge. Tentative date to haul was Wed. February 28th, but ground was still too soft. Set up a contingency with Montgomery County Western Regional to haul to their facility if we are unable to haul to field.
  11. Empty Village owned trash cans.
  12. Orientation of newly hired part-time laborer.
  13. Replace splitter valve on dump truck.
  14. Prep for snow fall.
  15. Clean shop.
  16. Slat roadway.
  17. Complete SWOP4G application.
  18. Invoice to park to complete Community Center well tie into ball diamond concession and restrooms.
  19. Contact Lakeside to order shear pins for clarifier.
  20. Contact MVL for estimate of when LED retrofit for street lighting would be completed. MVL states that it should be completed in the 3rd or fourth quarter due to large influx of communities upgrading street lighting.
  21. Locate water main on Farmersville West-Carrolton for water service tie-in.
  22. Deliver check to Prograde Construction for Hemple Rd Phase 3 project.
  23. Submit invoices and Warrants to Montgomery County for permissive tax disbursement. Once disbursement is received, the Village will have roughly $7200 out of pocket for the $400,000 street project.
  24. Start grant writing for OPWC 3rd water well project. If funded, the Village would be required to cover 25% of project cost. We can make up some of cost with in kind work as we did for Hemple Rd Phase 3.
  25. Repairs at WWTP.
  26. Read meters.
  27. Contact Kramer and Associates in regards to Interior Dry Water Tower Painting.
  28. Contact DP&L for billing discrepancy.
  29. Pull bacteria samples for distribution system.
  30. Pressure test at residence on California St. Found that pressure issue was due to faulty water softener.
  31. WWTP sample pulled.
  32. Run test on Iron/Manganese on distribution system.
  33. Prep to set floats at Elm St lift station.
  34. Replace pump motor at Hemple Rd lift station.
  35. Stripe parking lot at park.
  36. Replace floats at Elm St lift station.
  37. Check lockset to replace at parks.
  38. Complete bi-weekly report.
  39. Email Zenner in regards to water meter questions.

February 10th, 2020 - February 24th, 2020

January 27th, 2020 - February 10th, 2020

January 13th, 2020 - January 27th, 2020


2019

December 23rd, 2019 - January 23th, 2020

December 9th, 2019 - December 23rd, 2019

November 25th, 2019 - December 9th, 2019

October 28th, 2019 - November 25th, 2019

October 16th, 2019 - October 28th, 2019

September 23rd, 2019 - October 15th, 2019

September 9th, 2019 - October 15th, 2019

August 12th, 2019 - September 9th, 2019

July 8th, 2019 - August 12th, 2019

June 10th, 2019 - July 8th, 2019

May 28th, 2019 - June 10th, 2019

May 13th 2019 - May 27th 2019

April 22nd, 2019 - May13th, 2019

April 8th, 2019 - April 22nd, 2019

March 26th, 2019 - April 8th, 2019

March 11th, 2019 - March 25th, 2019

February 25th, 2019 - March 11th, 2019

February 11th, 2019 - February 25th, 2019

January 28th, 2019 - February 11th, 2019

January 14 th, 2019 - January 28th, 2019

December 10th, 2018 - January 14th, 2019


2018

November 26th, 2018 - December 10th, 2018

November 13th, 2018 - November 26th, 2018

October 22nd, 2018 - November 13th, 2018

October 8th, 2018 - October 22nd, 2018

September 24th, 2018 - October 8th, 2018

September 10th, 2018 - September 24th, 2018

August 14th, 2018 - September 10th, 2018

July 10th, 2018 - August 13th, 2018

June 11th, 2018, - July 9th, 2018

May 29th, 2018 - June 10th, 2018

May 14th, 2018 - May 29th, 2018

April 23rd, 2018 - May 14th, 2018

April 8th, 2018 - April 22nd, 2018

March 26th, 2018 - April 9th, 2018

March 12th, 2018 - March 26th, 2018